How Much Have Big Tech Companies Signed in Data Center Leases Not Yet on Their Books?
Our math totals about $774B of uncommenced leases across Alphabet, Meta and Oracle. Dates and scopes differ. Learn what the disclosures do and do not mean.
Bottom line for founders
Alphabet, Meta and Oracle report large lease commitments that have not started yet. Our math adds their listed sums to about $774 billion, but the dates and asset scopes differ. This is not one clean total for data centers alone. Read what was signed, when it starts and what cash must meet it.
By Domenic Giovanzana, Founder and General Partner
A company can sign for years of space before it can use the site. The bill is real enough to plan for, but the lease has not started. If we look only at today's balance sheet, we miss that next chapter.
The tension is not whether the figures are hidden. These companies show them in their notes. The useful question is how signed future costs line up with future cash.
The short version
- Alphabet reports $130.5 billion and Meta about $355.73 billion at September 30, 2026.
- Oracle reports $288 billion at August 31, 2026. Our sum is $774.23 billion, rounded to about $774 billion.
- The scopes differ. Meta and Alphabet include infrastructure beyond data centers.
- Guarantees and future revenue are separate measures. Neither turns this sum into automatic debt or expected loss.
Signed does not mean started
A lease commitment is a promise to make future payments under a lease. A lease starts when the tenant can use the asset. Signing can happen before that point.
A recognized lease liability is the amount recorded on the balance sheet under lease accounting. It reflects the lease payments under those rules, including discounting. Discounting puts future cash payments into a value for today.
That is different from simply adding every future rent check. The filings here list extra leases that have not started, apart from the lease liabilities already recorded. This is a timing distinction in the accounts, not proof of evasion.
The likely reason a builder signs early is to secure capacity before the site is ready. But that motive is an inference, not a stated reason for every contract in these filings. The disclosed numbers tell us the size of the promise, not each site's business case.
Three filings, not one uniform measure
Here are the listed sums for leases not yet commenced. The table keeps the dates attached to each figure.
| Company | Reporting date | Not yet commenced | Scope |
|---|---|---|---|
| Alphabet | Sep 30, 2026 | $130.5B | Mainly data centers and energy |
| Meta | Sep 30, 2026 | About $355.73B | Several infrastructure types |
| Oracle | Aug 31, 2026 | $288B | Substantially all data centers |
| Our math | Mixed dates | $774.23B | Mixed scopes |
Our math: $130.5 billion plus $355.73 billion plus $288 billion equals $774.23 billion. Rounded, that is about $774 billion. It is our sum of three disclosures, not a figure reported by one company.
It is not a measure of all big tech commitments. Nor is it a total of future AI spending. It covers the lease sums below, with different dates and scopes.
Alphabet: mostly data centers and energy
Alphabet's September 2026 quarterly filing, lease note says: "we have entered into leases, primarily related to data centers and energy infrastructure, that have not yet commenced with future lease payments of $ 130.5 billion that are not yet recorded."
The filing says those leases start between 2026 and 2031. Their terms range from one to 26 years. Mostly data centers and energy does not mean exclusively data center buildings.
Alphabet separately reports recorded operating lease liabilities of $20.508 billion and finance lease liabilities of $3.705 billion. Operating and finance are two accounting classes of lease. Together they total $24.213 billion, or about $24.2 billion.
Those recorded amounts are not an extra component in our $774 billion sum. They are a separate line. We do not treat a ratio between undiscounted future payments and recorded liabilities as a clean measure of debt growth.
Meta: a broader infrastructure scope
Meta's September 2026 quarterly filing, leases and promises under contracts describes operating and finance leases that have not started. It states: "These lease obligations were approximately $ 355.73 billion".
That scope includes data centers, energy infrastructure, colocations and network infrastructure. Colocation means space for equipment in a shared facility. It is broader than a count of stand alone AI campuses.
These leases are due to start from the rest of 2026 through 2036. The terms range from more than one year to 30 years. We do not use those end points to guess an average rent bill.
Meta also discloses other promises under contracts, separate from this lease discussion. A purchase commitment is a promise to buy goods or services, not necessarily a lease. Adding every such line to our lease sum would change what we were measuring.
Oracle: substantially all data center arrangements
Oracle's August 2026 quarterly filing, lease note states: "we had $ 288 billion of additional lease commitments, substantially all related to data center arrangements".
The leases are generally expected to start between the second quarter of fiscal 2027 and fiscal 2029. Their terms run fifteen to nineteen years. These are fiscal year references from Oracle's filing, not a calendar year forecast we have made.
Oracle separately lists recorded operating lease liabilities of $34.621 billion and finance lease liabilities of $9.185 billion. Our addition gives $43.806 billion, or about $43.8 billion. Again, that recorded sum stays outside our total of leases not yet commenced.
Meta's guarantee is another layer, not another rent total
Meta's venture note says: "In addition, we have provided residual value guarantees (RVG) to each of the Ventures."
A residual value guarantee is a promise to cover a value shortfall under specified conditions. Residual value is what an asset is worth at a later point. A maximum guarantee amount is a ceiling on exposure, not a forecast of cash that will be paid.
Meta's table for its unconsolidated data center ventures lists $41.493 billion of maximum residual value guarantees at September 30, 2026. Unconsolidated means the venture's accounts are not combined line by line into Meta's own accounts.
The same table totals maximum exposure of $68.404 billion. It includes the guarantee amount, $18.476 billion of lease commitments, $3.703 billion of future funding promises and $4.732 billion of equity carrying value. Carrying value is the investment amount on the books.
Do not add $41.493 billion to $68.404 billion: the guarantee is already inside that total. Do not add either amount to our $774 billion lease sum. We have not established a separate bucket with no overlap that would support that addition.
The table is maximum exposure across those ventures, not Texas alone. It is neither expected losses nor debt automatically due today. Our Hyperion financing walkthrough explains how a venture and a guarantee fit together.
Oracle's revenue promise is not cash in hand
A cost commitment has another side: what will pay for it? Oracle's filing says: "Remaining performance obligations were $ 664 billion as of August 31, 2026".
Remaining performance obligations, or RPO, means contracted revenue still to be earned under that accounting rule. It is not cash already collected. It is also not a label for revenue from just the leased sites in this table.
Oracle expects about 13% to become revenue in the next twelve months. Most is expected later. That timing matters more than a simple claim that the revenue total exceeds the lease total.
We do not divide $664 billion by $288 billion and call it coverage. One number is future revenue across Oracle's reported work still to be done. The other is a subset of future rent costs, with its own schedule. Revenue is not profit or cash available after all other costs.
The likely attraction of signed demand is a clearer basis for planning than hoped for sales alone. But it does not remove build, timing or cash collection risk. Our neocloud financing discussion explores why the source of cash matters.
Our view: the useful story is not hidden debt, but the gap between signing a cost, starting to use the asset and collecting the cash to pay for it.
A promise is not a bill due today
The three lease sums do not tell us how much rent falls due next month. They do not tell us how much cash each site will earn. They do not tell us whether a guarantee will be called.
Those are three separate questions. Keep them apart. A ceiling on loss is not a base case. A sales total is not cash after costs. A lease start date is not the day the lease was signed.
We can learn from the scale of the deals without using one big sum to stand in for all of those facts.
Read the dates, not just the big number
Try a plain cash test. When does rent start? When can the site be used? When will customers pay? A signed deal answers some questions, but it does not answer them all.
If cash comes in before rent is due, that is one kind of plan. If rent comes first, the company needs a way to fund the gap. If the dates can change, the plan needs room for that too.
This is not a claim about any one site in the filings. We have not mapped those sites or matched each lease to a customer. It is a way to read the notes without mistaking a promise to pay for a bill due now.
What a software founder can take from this
A GovTech software owner need not copy a giant lease program to use the lesson. Keep promises to spend beside expected receipts. Then ask which dates are firm and which remain a forecast.
Our working capital post says: "Signed government contracts that pay slowly create a timing problem more often than a growth problem." See working capital vs growth capital.
That does not make every signed obligation a timing problem. A large build whose payoff is not yet scheduled can be a growth need. The size of the contract alone does not settle that choice.
Use a revolving line of credit if you have recurring dated waits on signed contracts. Use loans with bullet payments if you have one large dated cash inflow.
Use growth capital if demand calls for more people, product or reach before cash returns on a firm schedule. Do not call that merely a late invoice. Our capital stack guide explains how different claims fit together.
Start with the cash gap, not the headline total. Our cash flow gap guide puts it plainly: "Your cash flow gap is a number, not a feeling."
Frequently asked questions
What does a lease not yet commenced mean?
It is a signed lease that has not started. The filings distinguish those future commitments from lease liabilities already recorded on the balance sheet.
Is about $774 billion a disclosed data center total?
No. It is our math: $130.5 billion for Alphabet, $355.73 billion for Meta and $288 billion for Oracle. The dates and asset scopes differ, and the scopes include more than data centers alone.
Is this hidden debt?
No. These amounts are disclosed in filing notes. A lease that has not started is distinct from a lease liability on the books.
Are Meta's maximum guarantees expected losses?
No. Maximum exposure is not an expected loss forecast or automatic debt. The guarantee amount is already included in Meta's venture exposure total.
Does Oracle's RPO prove its leases are fully covered?
No. Contracted revenue still to be earned is not cash in hand. Its scope and timing differ from those of the lease commitments.
What should a software founder take from this?
Match costs to expected cash dates. Use timing tools for dated waits and growth capital for a growth need, rather than assuming every signed commitment creates the same cash problem.
Related reading
- Software company financing strategy
- Working capital vs growth capital for GovTech software
- Capital stack seniority for GovTech software
This post is general education, not financial, legal, or tax advice.