The Agency Asked Me to Do Extra Work. Can I Invoice Before the Modification Is Signed?
A program manager email is not a payable contract change. Invoice extra government work after a written, priced modification, and size cash to signed work.
Bottom line for founders
A program manager email is not a contract modification. On federal contracts, only a contracting officer can execute a written change. On many federal commercial software contracts, changes may be made only by written agreement of the parties. Federal policy says those changes should be priced before they are signed, if that can be done without harm to the government's interest. If a significant cost increase is at stake and time does not permit a price, they should at least be given a ceiling price, unless impractical. A ceiling price is not cash already owed. California's purchasing manual says verbal notices cannot modify a contract. It also says an amendment must be issued before performance. Texas will not pay added amounts on a modified state agency contract without an added benefit. Ask for a written, priced change. Size cash to signed work, not to unsigned extras.
By Domenic Giovanzana, Founder and General Partner
A founder has a signed $480,000 government software contract. Mid period, a program manager emails a request for extra setup work. The CEO prices it at $80,000. The team staffs the work and sends an $80,000 invoice. The invoice comes back. No written change has been signed. Payroll still runs. Hosting still bills.
The reason is simple. An email is not a contract change. The request may be real. The cash is not. Not yet. Until a written, priced change is signed, the extra work is not contracted cash. The signer must have the right to bind the agency.
The short version
- On federal contracts, only a contracting officer can execute a written change.
- On many federal commercial software contracts, changes need written agreement of the parties.
- California's purchasing manual and Texas state agency rules also require a formal change before extra work is payable.
- Ask for a written, priced change. Size cash to signed work, not to unsigned extras.
The direct answer
Usually no. On many federal commercial software contracts, changes may be made only by written agreement of the parties. Only a contracting officer can sign a federal written change. California's purchasing manual says verbal notices cannot modify a contract. It also says an amendment must be issued before performance. Texas limits added payments on a modified state agency contract to cases with an added benefit. Size cash to signed, priced work.
A few words you will hear
- Contract modification: a written change to a signed contract. It must be signed by someone with the power to bind the agency. An email is not one.
- Contracting officer: the federal official with the power to enter, run, or change the contract. A program manager usually cannot sign that change.
- Written agreement of the parties: both sides must agree in writing before terms change.
- Unpriced change order: a written change issued without a settled price. It still needs a later priced agreement. It is not, by itself, a finished amount you can collect.
What counts as extra work on a signed government contract?
Extra work is added scope, added outputs, or changed terms that are not already in the signed contract. A customer's request does not, by itself, change the contract. Until a written, priced change is signed, that work is not contracted cash. The signer must have the right to bind the agency.
Consider our example. A software company has a signed $480,000 government software contract. This is an example, not a real company. Mid period, a program manager emails a request for extra setup work. The company prices it at $80,000. No written, priced change has been signed. The $80,000 is not, by itself, a payable contract change.
Federal policy is clear. Only a contracting officer, acting within the scope of that role, can sign a contract change for the government. (FAR 43.102)
On many federal commercial software contracts, the rule is just as plain. "Changes in the terms and conditions of this contract may be made only by written agreement of the parties." (FAR 52.212-4)
That clause applies to federal commercial product and commercial service contracts that include it. It does not apply to every government software contract. Read your contract.
Can you invoice before the modification is signed?
Most of the time, no. You cannot collect the extra work as a claim until a written, priced change is in place. Federal policy says those changes should be priced before they are signed, if that can be done without harm to the government's interest. If a change order is issued without a price, it still needs a later priced agreement. That officer must also secure any added funds before adjusting the contract.
If a significant cost increase could result, and time does not permit a price, at least a ceiling price should be set unless impractical. (FAR 43.102) A ceiling price is not cash already owed.
These next rules apply only once a change order has actually been issued and is not yet priced. They do not apply to a commercial contract that requires written agreement of the parties. They also do not apply if that contract has no one sided change order. When change orders are not priced in advance, they need two documents. One is the change order. The other is a later priced agreement that sets the resulting change in contract terms. If more funds are required because of the change, that officer shall secure the funds first. No adjustment to the contract comes before that. (FAR 43.204)
An unpriced change order is not a finished amount you can collect.
| Item | Amount |
|---|---|
| Signed contract | $480,000 |
| Extra work requested by email | $80,000 |
| Amount payable for that extra work until a written, priced modification is signed | $0 |
| Amount to size a timing tool to now | The $480,000 signed work and its payment lag |
This is our example under FAR 43.102 and FAR 52.212-4. Two figures matter here. One is signed. One is not. Size a timing tool to the $480,000 signed work and its payment lag. Do not size it to the unsigned $80,000. If a written, priced change is later signed for $80,000, that sum can then be a timing problem. So can its payment lag.
Does an email from the program manager authorize payment?
Usually no. On federal contracts, only a contracting officer acting within that role can sign a written change. Other government staff shall not sign those changes. They also shall not act in a way that causes the contractor to believe they can bind the government. They shall not direct or encourage the contractor to perform work that should be the subject of a contract modification. (FAR 43.102)
Ask the contracting officer whether a written, priced change has been issued. Talk to counsel before you start or continue unsigned work. Work done without a signed change is at the company's risk. That is not advice to start the extra work as a tactic.
What do California and Texas require?
They do not copy the federal contracting officer rule. They also require a formal change before extra work is treated as payable. California's purchasing manual says verbal notices cannot be used to modify a contract. It also says an amendment must be issued before the contractor performs. Texas says a state agency may modify a contract. It may not agree to make added payments without an added benefit. It also may not pay more for work the existing contract already required.
The California text is DGS manual guidance. It is not a statute. Do not assume every contract in the state uses this exact page. It does not, by itself, cover every city or county contract. Ask your agency.
The purchasing manual says: "Verbal notifications between buyers and suppliers cannot be used to modify a contract." It also says an amendment must be issued in advance of contractor performance. That includes receiving any goods or services before an approved amendment. (California DGS purchasing manual, section 18.05)
Texas is different again. This is a payment limit on Texas state agency contract changes. It is not the federal contracting officer rule. It does not cover every city or county contract.
The Comptroller says a state agency may modify a contract. It may not agree to make added payments without an added benefit in return. The same page adds this. Added funds for performance already required by an existing contract may not be paid by a state agency. (Texas Comptroller guidance on payments under modified contracts)
Ask your agency which rule applies. Local rules differ. Read your contract.
The email is not the cash
Start with two numbers, not one.
Write down the amount already under the signed, priced contract. Then write down the extra work that is only in an email. The first number is the one you can plan on, until a written, priced change is signed.
The signed amount is a cash number. The email amount is a request. Treat them as two files, not one. Do not mix them.
If a written, priced change is missing, ask for it. Without it, the extra work is not contracted cash. Do not bill the email. Do not fund the email.
What should you do this week?
- Read the changes clause. Write down who can sign the change, and whether changes require written agreement of the parties. If the issue is an expired term or an unsigned renewal, that is a different problem. See contract renewal lapse.
- Ask the contracting officer, not only the program manager, whether a written, priced change has been issued. Ask whether funds for it have been secured. Track status with invoice payment status tools.
- Invoice only against signed, priced work. If an invoice is already on hold because a purchase order ran out of money on work already in the contract, that is a different fix. See purchase order balance and invoice holds.
- If the agency still has to put money against a new change, that can follow the fiscal calendar. See government fiscal year 2027.
- If pay setup is still incomplete, see vendor registration and EFT payment.
Interest clocks after a late payment are covered in prompt payment laws for GovTech vendors. That post owns the interest mechanics. This one owns signed work versus unsigned extras.
Our view: unsigned extra work is not a bill you can size to.
Ask the contracting officer, not only the program manager, whether a written, priced change has been issued. Fund signed, priced work. Do not raise growth capital against an email.
Should you finance unsigned extra work?
Usually no. Unsigned extra work is not contracted cash. If you have a payment lag on amounts already under a signed, priced contract or change, that is a timing problem. If you need cash to build or sell more, that is a growth problem. Size the tool to signed work. Do not size it to an email.
Start with a basic line from our working capital post.
"Signed government contracts that pay slowly create a timing problem more often than a growth problem." (Working capital vs growth capital for GovTech software)
Size the gap first.
"Your cash flow gap is a number, not a feeling." (The government contractor cash flow gap)
| If you have | It is likely | Use |
|---|---|---|
| A payment lag on work already under a signed, priced contract or modification | Timing | A timing tool sized to that amount |
| Recurring signed modifications with a payment lag each cycle | Timing | A revolving line of credit |
| One signed, priced modification with a dated collection date | Timing | Loans with bullet payments |
| A need to build or sell more, not a wait on unsigned extra work | Growth | Growth capital |
Use growth capital only if the real problem is building or selling more. Unsigned extra work is not that problem by itself. For how claims stack, see capital stack seniority for GovTech software. Strategy hub: software company financing strategy.
Frequently asked questions
Can you invoice extra work before the government signs a modification?
Usually no. On many federal commercial software contracts, changes may be made only by written agreement of the parties. Only a contracting officer can sign a federal written change. State rules often require a formal amendment before extra work is payable. Read your contract and ask your agency.
Does a program manager email count as a contract modification?
Usually no. Federal policy says only contracting officers acting within their role may sign those changes. Other government staff shall not direct or encourage work that should be the subject of a modification.
What if the agency issued a change order without a price?
That is not a finished amount you can collect. Federal contract rules say an unpriced change order still needs a later priced agreement. That officer must secure any added funds before adjusting the contract.
Is this the same as a purchase order that ran out of money?
No. A PO balance hold is about reserved funds on work already in the contract. Extra work is about scope that is not yet in a signed, priced modification. Different fix.
Should you raise growth capital against unsigned extra work?
Usually no. Size a timing tool to signed, priced work and its payment lag. Keep growth capital for growth.
Do California and Texas use the same federal contracting officer rule?
No. California's purchasing manual says verbal notices cannot modify a contract and that an amendment must be issued before performance. Texas limits added payments on a modified state contract to cases with an added benefit. Local rules differ.
Related reading
- Contract renewal lapse
- Purchase order balance and invoice holds
- Working capital vs growth capital for GovTech software
- Government fiscal year 2027 for software vendors
This post is general education, not financial, legal, or tax advice.