The Government Issued a Stop Work Order. Can I Still Get Paid?

A stop work order can pause remaining work. It does not, by itself, cancel invoices already accepted. Size cash to amounts still collectible.

Bottom line for founders

A written stop work order can pause all or part of the remaining work on a signed government contract. It is not, by itself, a termination. It does not, by itself, cancel invoices for work already accepted. You must comply at once and take reasonable steps to minimize costs. Ask the payment office which invoices can still be processed. Size cash to amounts that are still collectible. Do not raise growth capital against work that is stopped.

By Domenic Giovanzana, Founder and General Partner

A founder is mid performance on a signed federal software contract. $80,000 in invoices for work already accepted is unpaid. The agency issues a written stop work order covering the remaining work. The CEO treats the $80,000 as lost. Or the next thought is to raise growth capital against the remaining work. That treats the work as if it will continue on the old schedule.

The reason that frame fails is simple. The order can pause remaining work. It does not, by itself, cancel invoices for work already accepted. It also does not make the stopped work a sure amount you can collect on the old schedule.

The short version

  • If the clause is in your contract, a written stop work order can require you to stop all or part of the work for a stated period. You must comply at once.
  • The order is not a termination. It does not, by itself, cancel invoices for work already accepted. Ask the payment office.
  • Federal and California day counts differ. Do not mix them. An equitable adjustment, if you have a right to one, is a later written change, not a scheduled invoice.
  • Size cash to amounts that are still collectible. Do not raise growth capital against work that is stopped.

The direct answer

Maybe, for work already accepted, under the payment terms in the contract. A written stop work order can pause all or part of the remaining work. It is not, by itself, a termination. It does not, by itself, cancel invoices for work already accepted. You must comply at once and take reasonable steps to minimize costs. Size cash to amounts that are still collectible.

A few words you will hear

  • Stop work order: a written order, identified as a stop work order under the contract clause. It requires the company to stop all or part of the work for a stated period.
  • Equitable adjustment: a written contract change to the schedule, the price, or both. It applies if the order increased the time or the cost properly allocable to performance, and if the company asserts that right in time.

What is a stop work order, and do you have to comply?

If your contract includes the clause, a written stop work order can require you to stop all or any part of the work for a stated period. The order shall be specifically identified as a stop work order issued under the clause. You must comply at once. You must also take reasonable steps to minimize costs allocable to the covered work.

"Situations may occur during contract performance that cause the Government to order a suspension of work, or a work stoppage." (FAR 42.1301)

On a federal contract that includes the clause, the contracting officer may, by written order, require the contractor to stop all or any part of the work. That pause can last 90 days after the order is delivered, and for any further period the parties agree. The period in the clause may be shorter than 90 days. The order shall be specifically identified as a stop work order issued under this clause. (FAR 52.242-15)

Upon receipt of the order, the contractor shall immediately comply with its terms. The contractor shall also take all reasonable steps to minimize the incurrence of costs allocable to the work covered by the order during the period of work stoppage. (FAR 52.242-15)

Do not keep working on the covered work after a written stop work order covers that work.

This clause is not in every federal software contract. The contracting officer may insert it in contracts for supplies, services, or research and development. (FAR 42.1305) Issuance should be approved at a level higher than the contracting officer. (FAR 42.1303) Read the contract.

Can you still get paid for work already accepted?

A stop work order pauses covered work. It does not, by itself, cancel invoices for work already accepted. It also does not, by itself, promise that those invoices will be paid on the old date. Payment for accepted work follows the contract's payment terms. Ask the payment office which invoices can still be processed.

Consider our example. A software company is mid performance on a signed federal software contract. This is an example, not a real company. $80,000 in invoices for work already accepted is unpaid. The agency issues a written stop work order covering the remaining work. The $80,000 is not, by itself, canceled by the order. Payment still follows the contract's payment terms. Ask the payment office which invoices can still be processed.

ItemAmount
Invoices for work already accepted on a signed federal contract$80,000
Amount still unpaid$80,000
Amount to size a timing tool toThe $80,000, plus the lag until the payment office processes invoices that are still collectible under the contract
Remaining stopped workDo not size growth capital to this work as if it will continue on the old schedule

This is our example. Size a timing tool to the $80,000 and the lag. Do not treat those invoices as lost. Do not raise growth capital against the remaining work while it is stopped.

If the delay is acceptance of the work, not a stop work order, that is a different issue. See invoice acceptance. Prompt payment interest, where it applies, still depends on a proper invoice and the contract rules. See prompt payment laws for GovTech vendors. Track status with the payment office. See invoice payment status tools.

Is a stop work order the same as a termination, a funding stop, or a payment dispute?

No. A stop work order is a pause, often while the government decides what to do next. It shall not be used in place of a termination notice after a decision to terminate has been made. If the order is canceled or expires, you resume work. If the covered work is later terminated, settlement is a different path.

Federal policy says a stop work order shall not be used in place of a termination notice. That is after a decision to terminate has been made. (FAR 42.1303) If the order is canceled or the period expires, the contractor shall resume work. If the order is not canceled and the covered work is later terminated for the convenience of the government, reasonable costs resulting from the order shall be allowed in the termination settlement. (FAR 52.242-15) That settlement path is not this post.

An equitable adjustment, if you have a right to one, is not automatic. It is not the same thing as a scheduled invoice. Under the federal clause, the contractor asserts the right to the adjustment within 30 days after the end of the period of work stoppage. The contracting officer may act on a later claim before final payment. If the conditions in the clause are met, the contract is then modified in writing. Do not count on a set dollar amount or a set payment date for that change.

Federal and California day counts are not the same. Do not mix them.

RuleStop periodWindow to cancel or terminateWindow to assert an adjustment
Federal clause90 days, and that period may be shorterWithin that period, or any agreed extension30 days after the stoppage ends, or later before final payment
California information technology cloud termsUp to 60 days45 days, or any agreed extension60 days after the stoppage ends

Those California terms apply when that document is part of the contract, typically for California information technology cloud work. They are not a federal rule, and they are not in every California contract. Under those terms, the contractor asserts its right to that adjustment within 60 days after the end of the period of work stoppage. The State may act on a later proposal before final payment. The same terms also say: "The State shall not be liable to Contractor for loss of profits because of a Stop Work Order issued under this Section." (California information technology general provisions, Section 18) That loss of profits sentence is California only. Do not apply it to federal contracts that use FAR 52.242-15.

This is not the same as reaching the funded amount on an incrementally funded contract. See incrementally funded contracts. This is not the same as invoicing extra work before a modification is signed. See extra work and modifications. A vendor's right in some states to suspend work because an undisputed invoice is unpaid is the opposite direction. See prompt payment laws for GovTech vendors. Texas state contracts vary. Read the clause. Do not assume a single statewide stop work payment rule. Ask your agency. Rules differ.

The order pauses work. It does not settle the invoices.

Start with two questions, not one.

Which invoices are for work already accepted? Which work is now stopped? Those are different cash questions.

The first set may still be due under the contract's payment terms. The second set is not money you can plan on the old schedule. Do not mix them.

What should you do this week?

Read the written order and the contract clause, and confirm the order is identified as a stop work order. Stop the covered work at once and take reasonable steps to minimize costs. Then ask the payment office which invoices for work already accepted can still be processed. Write down the dates. Talk to counsel about whether to assert an adjustment.

  1. Read the order and the clause. Confirm what work is covered, and what work, if any, is not. After issuing the order, the contracting officer should discuss it with the contractor and change the order if needed. Ask for that discussion. (FAR 42.1303)
  2. Comply at once and minimize costs allocable to the covered work. Do not keep working on covered work.
  3. Ask the payment office which invoices can still be processed, and track status with invoice payment status tools.
  4. If you have subcontractors on the covered work, follow the order's guidance and your subcontract terms. See subcontractor payment from a prime.
  5. Track the period in the order, any extension, and the window to assert an adjustment. Under the federal clause, that window is 30 days after the end of the stoppage, unless the contracting officer acts later before final payment. Under the California cloud terms, where they apply, that window is 60 days. Talk to counsel. Do not invent a claim template. Do not treat accepted invoices as forfeited.

Our view: invoices for work already accepted may still be collectible, but stopped work is not money you can plan on the old schedule.

Comply with the written order. Ask the payment office what can still be processed. Size cash to amounts that are still collectible. Do not raise growth capital against work that is stopped.

Should you finance invoices during a stop work order?

If the $80,000 is still collectible under the contract's payment terms, the wait is a timing problem. It is not a growth problem. Size a timing tool to those invoices and the lag. Do not raise growth capital against remaining work that is stopped.

Start with a basic line from our working capital post.

"Signed government contracts that pay slowly create a timing problem more often than a growth problem." (Working capital vs growth capital for GovTech software)

Size the gap first.

"Your cash flow gap is a number, not a feeling." (The government contractor cash flow gap)

If you haveIt is likelyUse
Unpaid invoices for work already accepted that can still be paid under the contractTimingA timing tool sized to those invoices and the lag
Recurring clean invoices with a payment lag each cycleTimingA revolving line of credit
One remaining payable amount with a dated collection dateTimingLoans with bullet payments
A need to build or sell more, not invoices or work waiting on a stop work orderGrowthGrowth capital

Use growth capital only if the real problem is building or selling more. Invoices or stopped work waiting on a government decision are not that problem by themselves. For how claims stack, see capital stack seniority for GovTech software. Strategy hub: software company financing strategy.

Frequently asked questions

Do you have to comply with a government stop work order?

Yes, if your contract includes the clause and the written order is issued under it. You must comply at once and take reasonable steps to minimize costs allocable to the covered work. Read the order to see what work is covered.

Can you still get paid after a stop work order?

You may still be paid for work already accepted, under the payment terms in the contract. The order does not, by itself, cancel those invoices. It also does not, by itself, set a new payment date. Ask the payment office.

Is a stop work order the same as a termination?

No. It shall not be used in place of a termination notice after a decision to terminate has been made. If the order is canceled or expires, you resume work. If the covered work is later terminated, settlement is a different path.

Do federal and California rules use the same day counts?

No. The federal clause uses a 90 day stop period, which may be shorter. It also uses a 30 day window after the stoppage ends to assert an adjustment. California's standard information technology cloud terms, where they apply, use a period up to 60 days. They also use a 45 day window to cancel or terminate, and a 60 day assertion window. Read the contract.

Is this the same as pausing work because the agency has not paid you?

No. Some prompt payment laws give a vendor a right to suspend work for nonpayment after notice. That is the opposite direction from a government issued stop work order.

Should you finance invoices during a stop work order?

If amounts for work already accepted are still collectible, size a timing tool to those invoices and the lag. Do not raise growth capital against remaining work that is stopped.

This post is general education, not financial, legal, or tax advice.

About Lambda Capital

Lambda Capital provides growth capital to profitable software companies in GovTech and other vertical markets. We take a patient approach and invest for the long term.

Contact Lambda Capital

We read every note and reply to founders directly.

Domenic Giovanzana, Founder and General Partner

Domenic is the founder and general partner of Lambda Capital, where he invests in technology companies building for the long term.

More about the team